Projects

Atatürk Dam & HEPP (8x300 MW)

Şanlıurfa / Turkey

CLIENT: General Directorate of State Hydraulic Works of Turkey (DSİ)

PROJECT: ATATÜRK DAM AND HEPP (8x300 MW), ŞANLIURFA / TURKEY

CONTRACTOR: Noell GmbH / Germany, Sulzer-Escher Wyss Ltd. & Asea Brown Boveri Co. / Switzerland

SUB-CONTRACTOR: Noell GmbH and Çiltuğ Joint Venture

SCOPE:

  • Fabrication, sandblasting, painting, erection and testing of penstocks, supports and expansion joints
  • Pipe Diameter: Ø5.5 m-Ø8 m
  • Pipe Plate: 22-44 mm
  • Pipe Lenght: 650 mx8 Lines.

TOTAL WEIGHT: 26,600 Tons

TOTAL PAINTING AREA: 250,000 m2

COMPLETED IN: 1994